Construction of the plant for the production of Siemens gas turbine parts
Location: Leningrad region, Lomonosov district, Officers village, quarter 2
Customer: Siemens
General Contractor: Compact CJSC
Hydroteks Group has successfully completed the construction work on the project «Plant for the production of Siemens gas turbine parts». The complex of concrete works, including an installation of slab structures of 400 mm thickness and construction of non-standard foundations for equipment with tight tolerances, is made within a reasonable time and of proper quality.
We thank Compact CJSC and Siemens company for their trust.
Completed works:
Enabling works.
Construction of solid structures.
Construction of foundations for non-standard technological equipment, including foundations for the carousel machines.
Industrial concrete floors with strengthened top layer (more than 14,500 square meters).
The works were completed on time and of proper quality.
Address and Working hours
18th Line of Vasilievsky Island, 47A,
Saint-Petersburg, 199178, Russia
Mon-Fr: 9:00-18:00
Sa, Su: Weekend
Contact us:
For official letters and requests:
development@hydroteks.com
For orders of construction objects:
+7-921-886-46-43, inna@hydroteks.com;
+7-931-281-20-74, dm@hydroteks.com
Supply Department:
+7 (812) 493-58-11, snab@hydroteks.com